F-036 土业园地 (第036期) 2010.2.22
Field for Artificial Soil Technology(AST)(№036)
作者:李鹏飞 Author:Li Pengfei February 22, 2010
My Web:www.tuyelt.com Telephone Number:13043864167 |
人造土壤技术室内试验附图
Figures of artificial soil technology |
注解:1、原料 2、分选车间 3、不可用原料4、外运处理 5、可用原料 6、有机原料7、无机原料 8、半固态有机物 9、固态有机物 10、库房区 11、岩石类 12、建材类 13、粉煤类 14、 矿渣15、砖瓦陶瓷 16、其它库房 17、粉碎车间 18、粉碎研磨车间19、中高温厌氧发酵车间 20、储气罐 21、造土母质库房 22、消毒除臭车间 23、造土堆肥库房24、人造土壤混配车间 25、种植与检测实验室 26、人造土壤库房 27、外销 |
 |
Fig.1 Flow Diagram of Process of Artificial Soil
|
Note: 1-raw material, 2-selection workshop, 3-unusable material , 4-treatment by special process outside, 5-useable material, 6-organic material, 7-inorganic material, 8-semi-solid organic matter, 9-solid organic matter, 10-storehouse, 11-a kind of rock, 12-a kind of construction, 13 a kind of coal cinder, 14-slag, 15-brick,tile,pottery and porcelain, 16-storehouse, 17-workshop for cutting solid 18-workshop for pounding and grinding powder, 19-workshop for fermenting in anaerobic condition at medium-high temperature, 20-gas tank, 21-storehouse for parent materials manufacturing soil, 22-workshop for sterilizing and removing smell, 23-storehouse for compost manufacturing soil, 24-workshop for mixing and making of artificial soil, 25-laboratory for planting and examination, 26-storehouse for artificial soil, 27-to sell. |
 |
Note:Chinese-English bilingual phrase
图二:人造耕地模式图—Fig.2 Sketch of Artificial Cultivated Land
A型、B型、C型、D型、E型—Model A, Model B, Model C, Model D,
Model E,? 山坡度45°—hillside with a slope of 45 degrees, 降水收集区—area gathering precipitation, 排水系统—drainage system, A—
artificial soil, B—gravel, C—rock powder or other buried matter, D—
space water-retaining under ground, E—mountain body, F—waterproof
layer
|
|
|